1.

Which of the following procurement proposals can be created during an MRP Live planning run for externally procured materials? Note: There are 2 correct answers to this question.

A.
B.
C.
D.
Answer
A., D.
2.

What does SAP S/4HANA use to determine the sequence in which materials are planned?

A.
B.
C.
D.
Answer
A.
3.

Production planning and product costing are to be implemented in your company. Which organizational level must you choose for stock valuation?

A.
B.
C.
D.
Answer
C.
4.

Where can you enter a rounding profile? Note: There are 2 correct answers to this question.

A.
B.
C.
D.
Answer
B., D.
5.

Which of the following tasks does the system perform during reorder point planning? Note: There are 2 correct answers to this question.

A.
B.
C.
D.
Answer
C., B.
6.

What is the definition of an opening horizon?

A.
B.
C.
D.
Answer
B.
7.

Which of the following rules apply when configuring the enterprise structure? Note: There are 3 correct answers to this question.

A.
B.
C.
D.
E.
Answer
C., E., A.
8.

At which of the following organizational levels must you maintain a business partner master record for a supplier? Note: There are 3 correct answers to this question.

A.
B.
C.
D.
E.
Answer
B., A., D.
9.

What are some characteristics of the material ledger? Note: There are 3 correct answers to this question.

A.
B.
C.
D.
E.
Answer
C., E., B.
10.

Which of the following does the material type control? Note: There are 3 correct answers to this question.

A.
B.
C.
D.
E.
Answer
D., E., C.

All Questions

1 2 3 4 5 6 7 8 9 10

All Questions Answer

1- C,D
-
2- C
-
3- A
-
4- B,D
-
5- B,C
-
6- D
-
7- B,C,D
-
8- C,D,E
-
9- B,C,D
-
10- A,C,D
-

WhatsApp us